Back to Previous

Issue 23/24

Tag
Author
Date published
Price

Contents page

The Structural Engineer

A President’s year – 2011

The Structural Engineer

Chief Executive’s report on the Institution 2011

The Structural Engineer

Sean Carroll, University of Nottingham and prize winner in the poster category of the 2011 YRC, writes about his PhD research 1

The Structural Engineer

Full journal for volume 89 issue 23

The Structural Engineer

Precast concrete panel manufacturer Decomo SA, based in Mouscron, Belgium, is supplying its products to the biggest construction project in The Netherlands: The Ministry of Justice and Internal Affairs building in The Hague. Ian Farmer visited the plant to see its operation and reports on the progress on the JUBI building site

The Structural Engineer

Prof. Dennis Lam, School of Engineering, Design and Technology at University of Bradford and Vice Chair of the Institution’s Research Panel, highlights the current research on concrete filled composite columns

The Structural Engineer

With today’s emphasis on sustainable construction and traceability of materials it makes good sense to know where each and every component comes from with the certificates to prove it. CARES UK produces a guide on how to go about it.

The Structural Engineer

Explosive testing of full-size ultra-high performance fibre-reinforced concrete panels was conducted in 2008. These tests and a simplified single-degree-of-freedom analysis of the response of the panels are reported. Each panel measured 3.5m by 1.3m by 100mm thick. The panels were contained within a large concrete enclosure to minimise clearing around the sides from the blast wave and placed between 7m and 12m from a 100kg TNT equivalent explosive charge. Two of the panels were fabricated with different levels of steel fibre dosage. The remaining two panels were fabricated with steel fibres together with supplementary steel bar reinforcement. Numerical computer modelling was carried out using the ANSYS Autodyn package to predict the behaviour of the four panels before testing. Based on the predictive modelling, each panel was placed a suitable distance from the explosive charge so as to cause permanent damage but not total structural collapse.

The Structural Engineer

Verulam