Planning applications
HSE is a statutory consultee for planning applications that involve or may involve a relevant building. As part of their planning application to the local planning authority, applicants will need to show that they have:
-
considered fire safety needs relevant to land use planning for the proposed building
-
considered these needs at an early stage
-
incorporated your thinking into your planning application.
HSE provides local planning authorities with fire safety input on proposals. Examples of fire safety needs relevant to land use planning include:
As part of the building safety reforms, the Building Safety Regulator (BSR) will be the building control authority for high-rise buildings.
Design and construction
Before building work starts
Before starting any building work, applicants will need to submit a design application to Building Safety Regulator via the Gateway system. The application will include information that shows how the design will:
The application will need to show the assumptions that have been made about the occupied building once built. Any assumptions and proposals must be reasonable and justified.
Developments that are built in stages
Any proposals for phased construction or occupation should be agreed at the design stage. Construction work should not start on a phase or stage without approval from BSR.
During construction
Building work must not start until approved by BSR. There will be ongoing requirements, including:
-
site inspections at key milestones
-
​reporting certain occurrences
-
managing change
-
identifying and storing the golden thread of key information about the building.
Some changes in design may need further approval from BSR before works can proceed. Design and construction.
When the building is completed
At completion, BSR will:
-
assess the application against the building regulations
-
undertake final inspections of the completed building work
-
assess the documents to be given to the building owner.
On approval, BSR will issue a completion certificate.
Before occupation
After a completion certificate is issued, the building will need to be registered. An application to register the building should be made to BSR.
Residential units must not be occupied until the building is registered.
Building work carried out without approval
It will be an offence to start prescribed building work without Building Safety Regulator approval and the Regulator will have enforcement powers where breaches occur.
The Building Safety Regulator will carry out inspections during construction. This could involve site inspections, requesting information such as the golden thread, or change control log(s), or other evidence of building regulations compliance.
It will be able to undertake tests or take samples of building materials by cutting into or laying open building work and will be able to prohibit the covering up of work for a period.