Self-Climbing Platform

Structural Designer

Nuvia Ltd

Client Name

Sellafield Ltd

Location

Cumbria, UK

PRINCIPAL CONTRACTOR
Nuvia ltd

ARCHITECT
Nuvia ltd

KEY CONTRACTORS
Delta International sub contractors - Steeple jacks and SCP operators
Sanderson Watts - â€‹Consultants
Alimak - HEK site access specialists
Vinci Technologies - Friction material research and development

PROJECT DESCRIPTION

The self-climbing platform provides a stable base for demolition and utilises existing commercial technology. Friction alone supports the platform during use. It was successfully employed for a Sellafield nuclear stack retirement project.    

Judge's comment:

The platform was designed to demolish a 61m high stack that was positioned on top of the first-generation Magnox reprocessing plant building on the Sellafield Ltd site. The stack, built in the early 1950s, was seen as presenting an unacceptable risk to the building below and others in the vicinity. Its concrete surface was considered too fragile to fix into with any conventional platform.

The self-climbing platform, developed from a solution used at Battersea, gently grips the stack (thus avoiding damage) and climbs it like a slow-motion monkey. It incorporates three levels of platform (and a roof only when descending).

Material could not be allowed to fall from the platform, either inside or outside the stack. The gap between the work surfaces and the stack had to be closed at all times to avoid the risk of falling objects. The judges were particularly impressed at how this was achieved with clever but simple sectional circular work-surfaces that adjusted to the changing diameter of the tapering stack.

Contact us

Telephone: +44 (0)20 7235 4535
Email: [email protected]

Social media

      

© Copyright 2019 - The Institution of Structural Engineers, 47-58 Bastwick Street, London, EC1V 3PS, United Kingdom
Registered with the Charity Commission for England and Wales No. 233392 and in Scotland No. SC038263