Bangor Aurora Aquatic & Leisure Complex

Structural Designer

WYG | Wiehag

Client Name

North Down Borough Council (with funding support from Sport NI)

Location

Bangor (NI), United Kingdom

Images: © Donal McCann Photography

PROJECT DESCRIPTION

The Bangor Aurora Aquatic & Leisure Complex was opened to the public on the 23 March 2013 as one of a number of London 2012 Olympic Games legacy projects. The centrepiece of the complex is a 50x25m FINA international standard pool, the first of its kind in Northern Ireland, which can be sub-divided into three by the raising of steel clad booms, which are recessed into the base of the pool. The construction made use of a variety of structural materials including concrete, steelwork and timber, with each material chosen to provide a durable, robust and aesthetically pleasing structure. The sustainability objectives were achieved with the maximisation of energy efficiency and the effective management of water consumption, along with a reduction in CO2 emissions through a number of innovative features.

Judge's comment:

The wave-formed glulam timber roof structure spans over 43m, making it one of the largest glulam timber projects ever constructed in the UK. Since the opening, it has already had a significant positive impact on the wider community and, in particular, those elite swimmers with ambitions to compete at regional, national and international levels.

Contact us

Telephone: +44 (0)20 7235 4535
Email: [email protected]

Social media

      

© Copyright 2019 - The Institution of Structural Engineers, 47-58 Bastwick Street, London, EC1V 3PS, United Kingdom
Registered with the Charity Commission for England and Wales No. 233392 and in Scotland No. SC038263