Temporary Works Toolkit. Part 13: The importance of understanding construction methodology

Author: D. McBride (Robert Bird Group)

Date published

3 July 2017

First published: 3 July 2017

Price

Free

Access Resource

Added to basket

Back to Previous

Temporary Works Toolkit. Part 13: The importance of understanding construction methodology

The Structural Engineer
Temporary Works Toolkit. Part 13: The importance of understanding construction methodology
Date published

3 July 2017

First published

3 July 2017

Author

D. McBride (Robert Bird Group)

Price

Free

Access Resource

A structure in its permanent state cannot be ‘wished into place’. Appropriate consideration must be given to construction methodology so that permanent works can be optimised, temporary works minimised and trade interfaces simplified. The result can be programme enhancement, increased site safety and, overall, a more economic build. Indeed, in the UK, regulations place a statutory duty on permanent works designers to consider the construction methodology. Nonetheless, ‘It’s the contractor’s problem’ is a sentiment that is sometimes still apparent with regards to buildability.

This article presents a list of general, high-level considerations that relate to construction methodology and optimisation of temporary/permanent works, with a number of examples provided. The considerations listed are intended to aid permanent works design engineers in their understanding of the type of questions that need to be asked during the early stages of design.

Additional information

Format:
PDF
Pages:
5
Publisher:
The Institution of Structural Engineers

Tags

Temporary Works Toolkit Technical Issue 7

Related Resources & Events

The Structural Engineer
Temporary Works Toolkit. Part 6: Backpropping of flat slabs – design issues and worked examples

Temporary Works Toolkit. Part 6: Backpropping of flat slabs – design issues and worked examples

Last month’s article in the series covered the theory and detailed methods recommended for calculating backpropping loads. This article continues by discussing some of the design issues and preconceptions related to backpropping, and gives worked examples.

Date - 3 January 2017
Author - P. Pallett
Price - Free
The Structural Engineer
Temporary Works Toolkit. Part 11: Temporary works associated with precast concrete bridge beam const

Temporary Works Toolkit. Part 11: Temporary works associated with precast concrete bridge beam const

Current highway bridge designs in the UK tend to favour either composite steel girders with a precast or in situ concrete deck for long spans, or precast concrete beams with an in situ concrete deck for spans of less than 40m. This article considers temporary works, in particular the use of temporary supports, to precast concrete bridge beams during deck construction.

Date - 2 May 2017
Author - C. Bennion (Kier Group)
Price - Free
The Structural Engineer
Temporary Works Toolkit. Part 19: An introduction to the demolition of large stuctures

Temporary Works Toolkit. Part 19: An introduction to the demolition of large stuctures

This article provides a brief introduction to demolition practice in the UK, addressing the more technical aspects requiring engineering input.

Date - 1 August 2018
Author - A. Holdsworth (Andun)
Price - Free