CROSS Safety Report: Fire in roofs containing photovoltaic panels

Author: Collaborative Reporting for Safer Structures

Date published

3 June 2024

Price
Free
The Institution of Structural Engineers The Institution of Structural Engineers
Back to Previous

CROSS Safety Report: Fire in roofs containing photovoltaic panels

Tag
Author
Collaborative Reporting for Safer Structures
Date published
3 June 2024
Price
Free
The Structural Engineer
Author

Collaborative Reporting for Safer Structures

Citation

The Structural Engineer, Volume 102, Issue 6, 2024, Page(s) 24-25

Date published

3 June 2024

Author

Collaborative Reporting for Safer Structures

Citation

The Structural Engineer, Volume 102, Issue 6, 2024, Page(s) 24-25

Price

Free

This month we present a report concerning the monitoring of photovoltaic panels and lessons learned from current experience.

Additional information

Format:
PDF
Pages:
24-25
Publisher:
The Institution of Structural Engineers

Tags

Safety Fire Roof Professional Guidance Issue 6

Related Resources & Events

The Structural Engineer
CROSS logo

CROSS Safety Report: RAAC planks found on pitched roof of 1990s hospital building

This month's CROSS report serves as a reminder to all engineers about the problems associated with RAAC planks and to be vigilant during any site inspections of existing buildings.

Date – 14 November 2022
Author – Collaborative Reporting for Safer Structures
Price – £0
The Structural Engineer
CROSS logo

CROSS Safety Report: Fire protection of light-gauge steel frames

CROSS-UK was expanded to cover fire safety reporting following recommendations by Dame Judith Hackitt in her post-Grenfell report Building a Safer Future . This month we present a fire safety report illustrating the implications of substituting a product within a tested system without further testing or justification.

Date – 1 June 2022
Author – CROSS
Price – £0
The Structural Engineer
Cross-laminated timber section of a building

CROSS Safety Report: The risk of collapse of multistorey CLT buildings during a fire

This month we present a report concerning multistorey cross-laminated timber buildings and their risk of collapse during a fire.

Date – 13 November 2023
Author – Collaborative Reporting for Safer Structures
Price – £0