Foreword

Author: C. Sexton (Crossrail Ltd)

Date published

2 July 2018

Price
Free
Access Resource

Added to basket

The Structural Engineer
Foreword
Date published

2 July 2018

Author

C. Sexton (Crossrail Ltd)

Price

Free

Access Resource
Author

C. Sexton (Crossrail Ltd)

I am pleased to have been asked to contribute a foreword to this timely publication. As work on the Crossrail
programme comes to a conclusion and we pass the baton of largest infrastructure project in Europe to High Speed 2, this is a valuable collection of insights into the design and construction process for the structural
elements of the programme. Crossrail has always been committed to sharing lessons learned, embodied most effectively in our Learning Legacy initiative, through which we have published many examples of insight and good practice on a dedicated website.

Additional information

Format:
PDF
Pages:
1
Publisher:
The Institution of Structural Engineers

Tags

Issue 7

Related Resources & Events

The Structural Engineer
<h4>A model railway station: implementing a 'kit of parts' solution to Custom House – the only above-gro</h4>

A model railway station: implementing a 'kit of parts' solution to Custom House – the only above-gro

The new Elizabeth line station at Custom House was a unique opportunity for design and construction. It is the only above-ground station on the central section of the line and will welcome millions of visitors to London’s largest conference centre, ExCeL, as well as providing vital connections for the Borough of Newham. A joint team from Crossrail Ltd, Atkins, Arup, Allies & Morrison, and Laing O'Rourke collaborated to develop the striking station design, creating a beacon for both the Elizabeth line and the local community. Faced with many constraints, a ‘kit of parts’ strategy was developed for Custom House’s construction, including prefabricated and standardised components. This approach – where much of the station was built off site – minimised workon site, drove down programme times and costs, and reduced the impact on the local community. The approach also led to Custom House’s excellent health and safety record – one of the best of any Elizabeth line station to date.

Date - 2 July 2018
Author - E. Newman-Sanders (Atkins), R. Smiley (Atkins)
Price - Free
The Structural Engineer
<h4>Editorial: Leaving a learning legacy</h4>

Editorial: Leaving a learning legacy

There is something special about megaprojects that brings out the best in engineering design and construction. It could be that the longer-term durations for the planning, design and build phases allow more measured and thoughtful decision making; it could be that the weight of public exposure and expectation creates an added incentive to succeed; it could be that the prestige of being part of the programme attracts the best teams in the best organisations; it could be that the extended schedule nurtures a team spirit and a collaborative way of working that is difficult to achieve in a typical shorter-term project.

Date - 2 July 2018
Author - G. Masterton
Price - Free
The Structural Engineer
<h4>Complete issue (July 2018)</h4>

Complete issue (July 2018)

All the articles from the July 2018 issue - a special issue on 'Structural engineering for the Elizabeth line'.

Date - 2 July 2018
Author - Various
Price - Free