Technical Guidance Note (Level 2, No. 23): Design of triangular timber trusses

Author: Chris O'Regan

Date published

18 November 2019

Price

Standard: £9 + VAT
Members/Subscribers: Free

Buy Now
Back to Previous

Technical Guidance Note (Level 2, No. 23): Design of triangular timber trusses

The Structural Engineer
Technical Guidance Note (Level 2, No. 23): Design of triangular timber trusses
Date published

18 November 2019

Author

Chris O'Regan

Price

Standard: £9 + VAT
Members/Subscribers: Free

Buy Now
Author

Chris O'Regan

A triangular timber truss is typically a specialist contractor design item that falls outside the responsibility of the structural engineer. Although trusses must comply with the design criteria for the building into which they will be installed, the sizing of these components and the connections within them usually falls under the remit of the contractor.

Nonetheless, in order to assess a truss design produced by a specialist contractor, the structural engineer needs to understand the theory underpinning the design.

This Technical Guidance Note offers advice on the design of triangular timber trusses. Due to the complexity of the subject, the advice given should not be regarded as comprehensive and readers are strongly encouraged to consult the reference materials listed at the end of this note.

Additional information

Format:
PDF
Pages:
4
Publisher:
The Institution of Structural Engineers

Tags

Technical Guidance Notes Technical Guidance Notes (Level 2) Technical Issue 11

Related Resources & Events

The Structural Engineer
<h4>Technical Guidance Note (Level 2, No. 18): Design of unreinforced masonry retaining walls</h4>

Technical Guidance Note (Level 2, No. 18): Design of unreinforced masonry retaining walls

This Technical Guidance Note is intended to act as an aide to those seeking to design an unreinforced masonry retaining wall. Following this guidance will prevent cracking and ensure that the wall performs as originally intended. The note will not cover the design of reinforced masonry retaining walls and variants of that form. Such reinforcement typically strengthens the wall itself against induced bending stresses and the wall’s geometry will therefore be somewhat different to that of an unreinforced retaining wall. The note will also not discuss the applied actions that a retaining wall will be subjected to, nor the construction of retaining walls. These subjects have previously been covered in the following Technical Guidance Notes: Level 1, No. 8: Derivation of loading to retaining structures and Level 1, No. 33: Retaining wall construction. It is assumed that the reader is familiar with the content of both these notes.

Date - 1 October 2018
Author - C. O'Regan (AECOM)
Price - £0/£9
The Structural Engineer
<h4>Technical Guidance Note (Level 2, No. 16): Design of reinforced concrete bored piles</h4>

Technical Guidance Note (Level 2, No. 16): Design of reinforced concrete bored piles

Piled foundations are one of the first aspects of scheme design a structural engineer needs to consider during a project's development. It is at this crucial stage that, without any specialist input, the structural engineer must make recommendations based on the typically limited knowledge they have on the subject. This Technical Guidance Note describes the method by which bored piles are designed using the current UK codes of practice, i.e. BS EN 1997 (Eurocode 7). It explains how to interpret soil conditions and design piles to match what has been discovered following a site investigation. The note does not address the types of piling systems that are available, nor the technical issues concerning their installation; these questions are covered in Technical Guidance Note Level 1, No. 23 Introduction to piling . The note explains how to design what is essentially a buried column of concrete to resist forces from the superstructure that are applied to it. It concerns the design of a single pile and not one that is part of a group. For information on how grouped piles differ in their design approach, the reader is directed to Cl. 6.3.3 of BS 8004:2015. (This article was update on 9 March 2018 to correct an error in Table 6.)

Date - 1 March 2018
Author - C. O'Regan (AECOM)
Price - £0/£9
The Structural Engineer
<h4>Technical Guidance Note (Level 2, No. 20): Design and detailing of lintels in masonry walls</h4>

Technical Guidance Note (Level 2, No. 20): Design and detailing of lintels in masonry walls

A significant-sized opening in a masonry wall will always require a lintel to bridge over it. This note offers advice on the different types of lintel that are available, their detailing requirements and their design.

Date - 1 March 2019
Author - C. O'Regan (AECOM)
Price - £0/£9