Enhanced demolition strategy for a 29-storey office building with mega transfer beams in Singapore

Author: K. Murugappan, Catherine Wong Chi Fun, Ngan See Pyng and Tan Chee Siew

Date published

1 July 2025

Price
Standard: £9.95 + VAT
Members/Subscribers: Free
The Institution of Structural Engineers The Institution of Structural Engineers
Back to Previous

Delayed destressing – an enhanced demolition strategy for a 29-storey office building with mega transfer beams in Singapore

Tag
Author
K. Murugappan, Catherine Wong Chi Fun, Ngan See Pyng and Tan Chee Siew
Date published
1 July 2025
Price
Standard: £9.95 + VAT
Members/Subscribers: Free
The Structural Engineer
Author

K. Murugappan, Catherine Wong Chi Fun, Ngan See Pyng and Tan Chee Siew

Citation

The Structural Engineer, Volume 103, Issue 7, 2025, Page(s) 24-32

Date published

1 July 2025

Author

K. Murugappan, Catherine Wong Chi Fun, Ngan See Pyng and Tan Chee Siew

Citation

The Structural Engineer, Volume 103, Issue 7, 2025, Page(s) 24-32

Price

Standard: £9.95 + VAT
Members/Subscribers: Free

This article presents the demolition strategy adopted for a 29-storey office tower in a highly built-up city area in Singapore.

Synopsis

This article presents the demolition strategy adopted for a 29-storey office tower in a highly built-up city area in Singapore. The building to be demolished had three major transfer beams, each 7.5m deep, spanning about 30m and supporting 15 storeys above them. Each weighed 1000 tons and was designed to support an estimated dead load of 3000 tons from the tower structure above. The transfer beams comprised post-tensioned strands, cast in reinforced concrete which encased steel trusses designed to take the massive load of the high-rise tower. Detailed study of the demolition sequence, involving an assessment of the overall stability of the supporting core structure, transfer beams and the temporary works, was carried out.

Instead of adopting the conventional method of reversing the construction sequence entirely and destressing the post-tensioned transfer beams first during the demolition, a delayed destressing approach was used. This approach had two significant advantages: ensuring the integrity of the transfer beams by not destressing while the upper floors were supported; and optimising the need for temporary works to support the transfer beams. Upon removal of the floors above, destressing of the transfer beams was carried out in stages, effectively supporting the self-weight and efficiently using the temporary propping.

Additional information

Format:
PDF
Pages:
24-32
Publisher:
The Institution of Structural Engineers

Tags

Multi-storey - tall structure Demolition Project Focus Issue 7

Related Resources & Events

The Structural Engineer
Blue abstract blocks

CROSS Safety Report: Poor retaining wall design

This month's report concerns a poorly designed retaining wall, immediately adjacent to a steel-framed multistorey building, which deflected and imposed significant lateral geotechnical loads into the building's superstructure.

Date – 1 July 2025
Author – Collaborative Reporting for Safer Structures
Price – £0
The Structural Engineer
Preparatory works for demolition of Huntingdon Railway Viaduct

Decommissioning of the A14 Huntingdon Railway Viaduct, Cambridgeshire

This paper describes the demolition of the central suspended span of the Huntingdon Railway Viaduct, which crosses the East Coast Main Line on the west side of the Cambridgeshire town.

Date – 4 January 2022
Author – Colin George, Mark Hatcher, Chris Law, Ionut Paunescu
Price – £9.95
The Structural Engineer
<h4>Reuse, build less, build lean: low-carbon design for 22 Bishopsgate, London</h4>

Reuse, build less, build lean: low-carbon design for 22 Bishopsgate, London

22 Bishopsgate was erected on the site of an abandoned project, reusing 100% of the existing foundations from three previous buildings, and incorporating more than 50% of the basement built for its predecessor. This article describes the approach to reusing the existing foundations and basement, as well as the focus on material efficiency in designing the superstructure and transfer structures.

Date – 2 September 2021
Author – Diego Padilla Philipps
Price – £9.95